Kenya, Ethiopia electricity interconnector to be completed mid 2019

By Meletus EZE

The Kenya and Ethiopia electricity transmission interconnector is set to be complete mid 2019, Joseph Njoroge, the Principal Secretary of the Ministry of Energy said on Monday.

Njoroge said this at an energy forum in Nairobi during the Third Meeting of the Programme Technical Steering Committee of the Project on the enhancement of a sustainable energy market in Eastern Africa-Southern Africa-Indian Ocean Region.

Njoroge said the 1045 kilometer line was 70 per cent completed on the Kenyan side and 90 per cent completed on the Ethiopian side.

“The project is expected to be completed in 2019 and will help to boost electricity trade in the East African region,” Njoroge said.

The Ethiopia-Kenya interconnector is a 500 KV High Voltage Direct Current (HVDC) line, with 612 KM on the Kenyan side and 433km on the Ethiopian side which is being funded by the African Development Bank.

Njoroge said the transmission line was initially meant to evacuate 400 Megawatts of power from Ethiopia to Kenya but negotiations are ongoing to revise the capacity in line with electricity demand in Kenya.

He noted that the Ethiopia-Kenya line is part of the East African power pool that seeks to connect the national electricity grids of eastern African countries in order to ensure energy flows from countries with surplus to regions of deficit.

 

Related posts

Airport Concession: No FAAN workers will be laid-off, FG assures

Abisola THOMPSON

‘Aero Contractors to resume after NCAA’s audit’

Our Reporter

FG Suspends Issuance of Licences for FTZs Operation

Our Reporter

EKEDC decries revenue losses over meter bypass in Lekki

Editor

Executive capitalism, the path to Nigeria’s prosperity

Dr Omaghomi Ofioritse

$8.4m fraud: Absence of oil marketers, companies stalls arraignment

Editor