Electricity Generation Companies (GenCos) comprising gas-fired and hydro stations said they could not generate 3,568 megawatts of electricity on Wednesday  due to unavailability of gas.

This information was made known  in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained in Abuja on Thursday  .

The report also noted that 110 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.

Similarly, it said that 603.3 megawatts was not generated due to high frequency resulting from unavailability of distribution infrastructure.

The report, however, said that the GenCos released an average of 4,149 MegaWatts/Hour of electricity into the national grid on Wednesday.

It said  the electricity sent out by the GenCos was down  by 226.51 megawatts from the 4,376 released on Tuesday .

The report revealed that the power sector lost an estimated N2,055 billion on Wednesday  due to insufficient gas supply, distribution and transmission infrastructure.

On sector reform and activities, it said that the dominant constraint for Wednesday  was unavailability of gas.

The report said  the peak generation attained on Wednesday  was 4,,640 megawatts.

 

 

Related posts

Mammoet Terminal Crane now operational at LADOL

Editor

At NBA Conference, Atiku, Obi, Shettima decry State of Nigeria, proffer solutions

Our Reporter

21 Customs desks/units crippling trade at Lagos Ports’

Our Reporter

World Bank, AfDB approved $2.83bn for Nigeria in 2021

Our Reporter

Fidelity Bank restates commitment to growth of real sector

Editor

DPR to enforce minimum industry safety training for downstream operations

Abisola THOMPSON