Fire incident affects 60 MVA TCN transformer in Alagbon  

Fire incident affects 60 MVA TCN transformer in Alagbon

 

By Yusuf Yunus

The Transmission Company of Nigeria (TCN) says a fire incident that occured on Wednesday evening has affected one of its 60MVA power transformers at  300MVA 330/132/33KV Substation, Alagbon.

Its General Manager, Public Affairs, Mrs Ndidi Mbah, disclosed this in a statement in Lagos.

Mbah said, “the incident happened at about 16:32hrs, on Wednesday.”

According to her, the operator on duty heard a heavy bang from the switchyard and immediately moved to the switchyard to investigate the sound and found fire under the cooling fans/fins of the transformer.

She said that frantic efforts were made to put out the fire with the fire extinguisher in the substation, but oil, which started dripping from the transformer, ignited the fire more.

“The engineer then switched off power supply in the substation on the 300MVA 330/132/33KV transformer and also made calls to the Federal Fire Service in Onikan and the Lagos State Fire Service at Dolphin Estate.

“The fire was put out at 17:35hrs by the fire services.

“From initial assessment, the transformer can be salvaged/repaired, and presently, the situation is under control,” she said.

Mbah said that normal supply to the station was restored at 7.25 p.m.

She said that all available transformers in the station had been restored.

According to her, Eko Distribution is on the ground for the management of the affected three no 33KV feeder, as we have redundancy in the station.

“All customers feeding from Alagbon 330/132/33KV substation will have supply tonight.

“The situation is under control, and TCN will do a comprehensive check of the affected transformer immediately to enable it properly asess the transformer for repair work.

“We are truly saddened by this incident, especially as the company had operated from the beginning of this year to- date without any system collapse or major incident such as this.

“Even as we have already mobilised our engineers to commence the transformer assessment and repair work immediately.

“We will endeavour to ascertain the trigger of this fire incident with the view to forestall such incident in our substations,” she added.

Related posts

TCN installs new transformer, circuit breaker in Suleja substation – Official

Meletus EZE

DPR warns IPMAN members against selling petrol above official pump price

Abisola THOMPSON

Bill Gates calls for innovation in reducing emissions

Editor

FG involves miners in N5bn intervention fund

Editor

How insecurity, weak fiscal policies drive Inflationary pressures

Our Reporter

Why Current Electricity Tariff Hike Is Fraudulent’

Our Reporter