TCN installs new transformer, circuit breaker in Suleja substation – Official

The Transmission Company of Nigeria (TCN) is set to install a new 33KV current transformer in Suleja Transmission Substation, Niger.

Mrs Ndidi Mbah, TCN’s General Manager, Public Affairs, said in a statement in Abuja on Sunday that the installation would also include a Circuit Breaker on its 30MVA, 132/33kV power transformer.

Mbah said the installation would be carried out in-house by TCN’s maintenance engineers between 10:00 a.m and 6:00 p.m on Monday.

“Meanwhile, the 45MVA, 132/33kV transformer 2 in the same substation will be temporarily interrupted for two hours within the proposed six-hour time frame to ensure safe working space.

“Consequently, there will be a planned interruption of bulk power supply to AEDC through the Suleja Transmission Substation to enable TCN engineers to carry out the installations.

“It is important to note that only 26 Mega Watts supplied at 33kV to the Abuja Steel Company will be interrupted during the installation,” she said.

Mbah said TCN has assured that power supply would be restored through the substation after the engineers have completed the installation.

Related posts

Imo ‘Refinery’ deaths: Buhari commiserates with victims’ families, orders clampdown on illegal refineries

Our Reporter

Quality, affordable real estate services possible, despite inflation – Expert

Our Reporter

Fidelity Bank Extends CSR Projects

Our Reporter

NCDMB’s PNC kicked off in golfing style

Emeka Ugwuanyi

Titan Trust Bank acquires 89.39% stake in Union Bank

Meletus EZE

Joshua Knocks out Pulev to Set up Clash with Fury

Our Reporter