Featured Transport

Lagos-Ibadan Expressway still 40% completed

As the Federal Government prepares for partial closure of the Lagos-Ibadan Expressway on Monday for repairs, the Federal Controller of Works in Lagos, Mr Adedamola Kuti, says the  project is still 40 per cent completed.

Kuti said in Lagos that the project, which began in 2013 and earlier scheduled to end in 2017, would now be completed by 2021/22 because the Muhammadu Buhari administration included some  missing features.

He listed the additional features to include under passes, foot bridges, flyovers, toll plazas and road expansion.

Kuti said that  the additional features shifted the completion date.

He added that the additional features made the completion level to still be at 40 per cent which it recorded months ago.

On the Ikorodu-Sagamu Road, expected to serve as an alternative route as construction work progresses on Lagos-Ibadan Expressway, Kuti said that the project was about 18 per cent completed.

He, however, added that critical sections of the highway likely to cause gridlock had been stabilised.

“The highway is about 18 per cent completed but I can tell you now for sure that there is great improvement on the road.

“What we did is, to first of all, tackle critical spots that cause traffic, and we are trying to link them up.,” he said.

He said that the ministry of Works, Housing and Power was working at night on some roads to ease gridlock.

“We have been fixing terrible but strategic roads. We are intervening here and there,’’ he said.

He noted that several road projects were abandoned in the past due to funding constraint, compelling the government to seek alternative sources of funding to fix more roads.

“A lot of projects were having difficulties getting appropriate funding but with other sources of funding, life has been brought  into one or two of our projects, and that is why you are seeing activities everywhere.

“Lagos-Ibadan Expressway is progressing, Apapa-Oshodi-Ojota-Oworonsoki Expressway Rehabilitation and Reconstruction project is on, and these are the critical roads that bind everybody, especially in Lagos, together,’’ he said.

According to him, contractors are no longer being owed.

“Now, it is open-ended for contractors to collect whatever is the worth of work done in any project.”

 

Related posts

EKSG reverses all last minute appointments by Fayose

Editor

FG to issue second Green Bond to finance 2018 budget – DMO

Editor

Ooni of Ife says women have potential to be president of Nigeria

Aliyu DANLADI 

FEC approves 0.2% new import levy, relishes continuing GDP growth

By Shile GIWA

We can’t confirm beneficiaries got N226.8bn intervention grants – AuGF

Our Reporter

Zamfara Govt uncovers 119-year-old on its payroll

Aliyu DANLADI