Electricity Generation Companies (GenCos) comprising gas-fired and hydro stations said they could not generate 3,323 megawatts of electricity on Wednesday  due to unavailability of gas.

This information was made known  in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained  in Abuja on Thursday.

The report also noted that 0 megawatt of electricity was not generated due to unavailability of transmission infrastructure during the period.

Similarly, it said that 1,319.8 megawatts was not generated due to high frequency resulting from unavailability of distribution infrastructure.

The report, however, said that the GenCos released an average of 4,002 MegaWatts/Hour of electricity into the national grid on Wednesday.

It said that the electricity sent out by the GenCos was up by 90 68 megawatts from the 3,911 released on Tuesday.

The report revealed that the power sector lost an estimated N2,229 billion on Sunday  due to insufficient gas supply, distribution and transmission infrastructure.

On sector reform/activities, it said that the dominant constraint for Wednesday  was unavailability of gas.

The report said that the peak generation attained on Wednesday  was 5,048.2 megawatts.

 

Related posts

Power intervention fund jumps to N2.9trn

Our Reporter

Nigeria yet to tackle basic water, sanitation challenges at 59 – stakeholder

By Shile GIWA

Sahara Group tasks petroleum engineers on Africa’s energy transition best policies

Emeka Ugwuanyi

OPEC cuts 2020 oil demand forecast, urges effort to avert new glut

By Abisola THOMPSON

DPR issues award letters to successful marginal field investors May 31

Editor

NSE: Market indicators up by 0.80% despite election

Editor