Electricity Featured

Electricity: Blackout persist as generation falls 39.78% to 2,464MW

The ongoing widespread blackout across the country will persist as power generation dropped by 39.78 per cent yesterday to 2,464.7 Megawatts as at 3pm from 4,097MW peak generation recorded on Sunday.

Data released by the National System Operator (NSO) showed that 16 plants were on the grid with Azura-Edo topping generation at 396MW. It was closely followed by Geregu NIPP with 391MW.

Other plants on the grid were Afam IV and V at 103MW, Afam VI at 131MW, Alaoji NIPP 101.7MW, Delta 110MW, Geregu NIPP 136MW, Ihovbor NIPP 94.90MW, Jebba Hydro 252MW, Olorunsogo 197.8MW, Omoku 47.7MW, Omotosho 147.30MW, Omotosho NIPP 88MW, 62.40MW, Paras Energy 62.40MW, Rivers IPP 150MW and Trans-Amadi 55.9MW.On the distribution side, data from the NSO showed that Ikeja DisCo had the highest allocation for the day with 556.06MW, followed by Eko DisCo with 434.44MW.Others were Ibadan DisCo (416.25MW), Abuja DisCo (349.64MW), Benin DisCo (273.63MW), Enugu DisCo (298.63MW), Jos DisCo (167.22MW), Kaduna DisCo (243.23MW), Kano DisCo (243.23MW), Port Harcourt DisCo (197.62MW) and Yola DisCo (106.61MW).

FG optimistic of sector’s improvement

The Federal Government has expressed optimism that the measures it has put in place in the past few months would boost grid power supply despite the setbacks recorded recently.The Chairman of the Nigerian Electricity Regulatory Commission (NERC), Engr. Sanusi Garba said government efforts to improve the capacity of the DisCos to take more power would soon have the necessary impact on the consumers.

Engr. Sanusi who spoke in Abuja explained that the Federal Government Power Sector Recovery Programme being executed in partnership with the World Bank has a Performance Improvement Plan which would see an estimated investment of N871 billion across the eleven DisCos.

“The Federal Government initiated the PSRP with the support of the World Bank to achieve the goal of Nigerians having access to adequate, reliable and affordable electricity in Nigeria.“Notwithstanding the electric power supply industry is now private sector driven, its relevance to economic growth and industrial development will require strategic government interventions. At this developmental stage, the industry’s challenges require that hands be on the deck to achieve an efficient and effective electric power supply industry that we desire for our economic development”.

He explained the objectives of PSRP to include the power sector’s financial viability, improve electricity supply reliability to meet the growing demand, strengthen the sector’s institutional framework, and implement policies that promote and encourage investors’ confidence, and institutionalise a contract-based electricity industry.

He pointed out that despite the challenges faced by the sector, “all the stakeholders involved in this power sector recovery programme are very much on track and are ready to do what we all need to both in terms of financial performance by the distribution companies and the issue of the off-taker.

“I am not saying we are at the destination yet but at least the trajectory is looking upward and great promise for service delivery to Nigerian consumers”.

Related posts

“US” debuts at No 1 at US box office

Editor

Nigerian engineers in Diaspora plan online training hub for local content development

Our Reporter

Domestic refining will end unstable petrol pricing –LCCI

Our Reporter

Exxon Mobil says will lower greenhouse gas emissions intensity by 2025

Meletus EZE 

Nigeria loses N231bn to dysfunctional refineries under Buhari

By Shile GIWA

Banks’ non-performing loans now N1.17tn – NBS

Our Reporter