GenCos fail to generate 3,133.9 megawatts due to unavailability of distribution infrastructure

Electricity Generation Companies (GenCos), comprising gas-fired and hydro stations said that they could not generate 3,133.9 megawatts of electricity due to unavailability of distribution infrastructure on Thursday .

This is contained in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained in Abuja on Friday.
The report also attributed the 3,133.9 megawatts not generated to high frequency.
It also noted that 40 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.
Similarly, it said that 1,674 megawatts was not generated due to unavailability of gas.

The report revealed that the power sector lost an estimated over N2.32 billion on Thursday due to insufficient gas supply, distribution and transmission infrastructure.
It however, said that the GenCos released an average of 3,587 megawatts-hour of electricity into the national grid on Thursday.
It said that the electricity sent out by the GenCos was up by 87.4 megawatts from the 3,500 released on Wednesday.
The report said zero megawatt was recorded as loss due to water management procedures.
On sector reform/activities, it said that the dominant constraint for Thursday was high frequency resulting from unavailability of distribution infrastructure.
The report said that the peak generation attained on Thursday was 4, 413.7 megawatts.

Related posts

China views yuan depreciation not in its interest: Mnuchin

Editor

CBN sanctions GTBank, UBA, Zenith Bank N175million for contraventions in 2019

Meletus EZE 

Presidency: we’ll soon reveal those behind crude oil theft in Nigeria

Our Reporter

London Stock Exchange extols Orjiako’s achievement at Seplat Energy

Emeka Ugwuanyi

MultiChoice mourns Desmond Tutu

Meletus EZE

Bandits abduct wife, daughter of Plateau Commissioner

Our Reporter