Electricity Featured

Nigeria needs 41 years to achieve stable power’

The Senate Committee on Power, yesterday, declared that it might take the next 41 years for the country to experience stable power supply due to underfunding and the Federal Government’s failure to fix the challenges of electricity generation.

It was stunned by the submission of the Minister of Power, Mamman Saleh, that of the N165b required for capital projects in 2020, N4b was given as bribe of which the only N3b was cash-backed.

The Committee, therefore, tackled the minister for raising hope on early provision of constant power supply, while Managing Director of the Transmission Company of Nigeria (TCN), Sule Ahmed Abdulaziz, painted a gloomy picture during the ministry’s budget defense.

A member of the Committee, Danjuma Goje, expressed concern that based on Abdulaziz’s presentation, N165b was proposed, but the ministry gave N4b envelope, insisting that it would take 41 years to deliver constant electricity when N165b is divided by N4b.

He said if ongoing projects being completed there is still no hope for stable transmission of power in the country.

“Going by the ministers presentation that transmission gas increased from 5000 to 8000 megawatts, it is not enough. When dishing out figures, we should bear in mind that capacity, transmission, and distribution have increased and that Nigerians, manufacturers, and industrialists want to see stable electricity.

 

Related posts

Abuja-Kadina Rail: FG Mulls Installation of Digital Security Network

Our Reporter

NCDMB, NEXIM sign agreement on $30m capital, capacity building fund

Abisola THOMPSON

Germany’s Mihambo sails to long jump gold, Nigeria’s Brume settle for bronze

By Shile GIWA

Anambra monarch lauds Obi’s choice as Atiku’s running mate

Editor

Nigerian Navy seizes 94,800 litres of illegal AGO in Akwa Ibom

Abisola  THOMPSON 

NLC, MAN, others kick against electricity tariff hike

Our Reporter