Electricity: GenCos fail to generate 1.631.5 megawatts due to gas shortage

The Electricity Generation Companies (GenCos), comprising gas-fired and hydro stations said that they could not generate 1,631.5 megawatts of electricity on Saturday due to unavailability of gas.

This is contained in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained in Abuja on Sunday.
The report also noted that 0 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.
Similarly, it said that 3,258.5 megawatts were not generated due to high frequency resulting from unavailability of distribution infrastructure.
The report, however, said that the GenCos released an average of 3,349 MegaWatts/Hour of electricity into the national grid on Saturday.
It said that the electricity sent out by the GenCos was down by 16.77 megawatts from the 3,365 released on Friday.
The report said zero (0) megawatts was recorded as losses due to water management procedures.
The report revealed that the power sector lost an estimated N2.34 billion on Saturday due to insufficient gas supply, distribution and transmission infrastructure.
On sector reform/activities, it said that the dominant constraint for Saturday was high frequency resulting from unavailability of distribution infrastructure.
The report said that the peak generation attained on Saturday was 4,093.4 megawatts.

Related posts

Bank robbery: FCT Police arrest fleeing gang member

Meletus EZE 

Gov. Dickson bemoans recall of N24bn Paris Club debt refund to Bayelsa

Editor

FG didn’t award Atala marginal field to new investors, says BOCL

Our Reporter

Lagos not paid derivation fund as oil producing state since 2018 — Commissioner

Abisola THOMPSON 

Domestic Airlines may lose N5bn as FAAN shuts Lagos Airport Runway for Lighting from today

Our Reporter

Nigeria now generates 13,000mw of power, says Minister

Abisola THOMPSON